Mellitah Completes Key Phase in $1.6 Billion Bouri Gas Project Ahead of Schedule
Mellitah Oil and Gas has completed a key phase of its $1.565 billion Bouri gas project ahead of schedule, with progress at 69% compared to the planned 62%. The milestone includes compressor installation on an offshore platform and supports Libya’s goal to reduce flaring by 2030.