Mellitah Completes Key Phase in $1.6 Billion Bouri Gas Project Ahead of Schedule

Mellitah Oil and Gas has completed a key phase of its $1.565 billion Bouri gas project ahead of schedule, with progress at 69% compared to the planned 62%. The milestone includes compressor installation on an offshore platform and supports Libya’s goal to reduce flaring by 2030.

By Editorial Dept Wed, May 6, 2026 at 6:33 PM GMT+3 2 min read · Yahoo Finance ·

Mellitah Completes Key Phase in $1.6 Billion Bouri Gas Project Ahead of Schedule

Topics: Bouri Gas Project gas flaring reduction Libya energy sector